Project Portfolio

A project portfolio combines several projects in one view. It is used for cross-project analysis of dates, resources, priorities, status, and risks.

Project portfolio in the Gantt chart

Prerequisites

  • Projects are local files, server projects, or cloud projects.

  • Projects use the same resource pool.

  • Categories, status values, priorities, and customers are maintained consistently.

Usage

A portfolio is used for:

  • cross-project resource planning

  • capacity balancing across several projects

  • portfolio overview

  • project prioritisation

  • simulations by including or excluding projects

  • variance analysis in portfolio context

Select projects for a portfolio

Difference From Summary Project

The portfolio is mainly used for common analysis and steering. The summary project is stronger for operational joint handling of several projects.