Baseline

A baseline is a saved reference state of a project. It is the basis for variance analysis, project controlling, and status reporting.

Add baseline from the menu

Contents

A baseline stores relevant plan values, for example:

  • dates

  • effort

  • costs

  • resource information

  • working time and calendar context

Usage

Baselines are used to compare current project values with an earlier approved planning state. Several baselines can document different planning states.

Select a baseline from the list

Dynamic Baseline

The dynamic baseline can use a suitable reference state per activity when several baselines exist. This is useful in longer projects with regular progress tracking and approved plan revisions.

Use a dynamic baseline