Entry Point for Construction Planners¶
This entry point is for project managers and planners in construction projects: building construction, civil engineering, plant construction, infrastructure, and related areas. Rillsoft Project supports the requirements of these industries: trades, capacity balancing, machinery planning, and long-term schedule control.
Typical Tasks in Construction Planning¶
build a construction schedule by trades or phases
link tasks with duration, waiting times, and overlaps
plan equipment, devices, and machinery and detect conflicts
check capacity utilization of subcontractors and internal staff
keep critical path and float visible in daily work
document dates for customers and authorities
save a baseline for target/actual comparison and report progress
Typical Working Path¶
1. Build project structure by trade
Structure the project into subprojects by trade, for example shell construction, roof, heating, electrical, and interior work. Each trade receives its own level with the related tasks.
2. Link tasks with waiting times and overlaps
Many construction tasks have real waiting times, for example concrete curing or screed drying. Use positive lag in finish-start dependencies. For overlaps, for example interior work starts while shell construction is still running, use negative lag.
3. Assign equipment, devices, and machinery
Crane, concrete mixer, excavator, or scaffolding are resources with limited availability. Create them as equipment, device, or machinery in the resource pool and assign them to tasks.
4. Perform capacity balancing
Check whether employee and equipment capacities are sufficient. Overloads become visible in resource views. Rillsoft Project can resolve overloads automatically through optimization, or you can move tasks manually.
5. Monitor the critical path
In construction projects, the critical path often shifts, for example when material deliveries are delayed or weather blocks external work. Check the critical path after every planning change.
6. Baseline and progress report
Save the baseline before construction starts. Record progress weekly, for example percent complete and actual effort, and compare it with the baseline.
Important Views for Construction Planners¶
View |
Use |
|---|---|
Gantt chart |
Daily work: tasks, bars, dependencies, critical path |
Equipment utilization |
Equipment and machine capacity over time |
Employee utilization |
Utilization of trade workers and subcontractors |
Network diagram |
Check process logic, especially for complex dependencies |
Portfolio bar chart |
Overview of all active construction projects in the company |
Information panel |
Overdue tasks, consistency checks, external documents such as plans and permits |
Typical Decisions¶
Situation |
Recommendation |
|---|---|
Concrete task needs three days curing time |
Finish-start dependency with lag +3 days. |
Interior work starts while shell construction still runs for ten days |
Finish-start dependency with lag -10 days. |
Crane is needed for two parallel tasks |
Use an incompatible task group or create the crane as machinery with capacity 1. |
Finish date cannot be reached |
Analyze critical path, check parallel execution, focus resources on critical tasks. |
Subcontractor provides dates as an Excel list |
Store external links or external documents in the information panel. |
Authority milestone must remain fixed |
Create the task as a milestone with a fixed date and make preceding float visible. |