Manage a Summary Project

A summary project is a Rillsoft Project mode in which several individual projects are edited operationally together. Unlike a project portfolio, which is primarily used for analysis, the summary project enables direct planning, resource assignment, dependencies, and corrections across project boundaries.

Note

The summary project requires Rillsoft Project with Rillsoft Integration Server. Without Integration Server, this function is not available.

When to Use a Summary Project

Use a summary project when:

  • several projects are edited by different teams at the same time

  • cross-project task dependencies must be maintained

  • shared resource utilization optimization across several projects is required

  • an existing project should be split into several separate projects

  • simulations with combined project contents should be performed

Important prerequisite: All projects in the summary project must use the same resource pool. Projects with deviating resources must be synchronized first.

Summary project Gantt chart

Create a Summary Project

Option 1: Create a new summary project

  1. Choose File > Open new summary project.

  2. The Rillsoft Integration Server summary project dialog appears.

New summary project in Rillsoft Integration Server
  1. Enter a name for the summary project.

  2. Use Filter to limit the project list.

  3. Select the folder where the required projects are stored.

  4. Select the projects to include in the summary project. You can also add projects from other folders.

  5. Click OK.

Summary project properties in Rillsoft Integration Server

After creation, the Rillsoft Integration Server summary project dialog shows all summary projects on the left. The new summary project is selected. On the right, you see the included projects.

The Project count column shows the total number of projects in the summary project. Available shows how many projects you can read.

Option 2: Create a summary project from a split project

If an existing project consists of several subprojects and should be converted into a summary project, check these prerequisites first:

  1. The project must contain at least one subproject.

  2. There must be no separate tasks on the top project level. All tasks must be below a subproject.

  3. There must be no added documents on the top project level.

If the prerequisites are met:

  1. Open the project.

  2. Choose Project > Rillsoft Integration Server > Split project.

Split project menu
  1. The dialog shows in Name how many separate projects the project can be split into.

Split project dialog
  1. In Path, click the three dots and select a virtual folder for each subproject.

  2. Click OK.

The original subprojects are saved as separate projects and automatically combined into a new summary project.

Open a Summary Project

  1. Choose File > Open > Rillsoft Integration Server > Summary project.

  2. The Rillsoft Integration Server summary project dialog appears.

Open summary project in Rillsoft Integration Server
  1. On the left, you see all summary projects with project count and availability information.

  2. On the right, you see the projects in the selected summary project. You can clear individual projects for this opening process.

  3. Projects with a red background are locked.

  4. Optionally select Read only to open projects read-only.

  5. Click OK.

Set project order

Click a column header in the dialog to sort projects by that characteristic. Available columns include project name, code, category, priority, status, start, finish, and file name. The selected order is used in the summary project.

Load baseline

If you do not need target/actual comparison in the summary project, clear Load baseline. This speeds up loading significantly.

Locking mode

  • Pessimistic: As soon as one user changes a project, others can open it only as a read-only copy.

  • Optimistic: Every user can edit the project at any time.

Work in a Summary Project

All views from Gantt chart to resource diagram are available in the summary project. You can create tasks, assign resources, correct workflows, and save results, as in a normal individual project.

Note: A new project cannot be created inside the summary project. New projects must be created separately and then added to the summary project.

Reload a Summary Project

When several people work in the summary project at the same time, reload it to see changes made by others.

Click the Reload icon in the Quick Access Toolbar.

Reload summary project

If the icon is not visible, use Customize Quick Access Toolbar and add the Reload command.

Add reload command to Quick Access Toolbar

Cross-Project Dependencies

In a summary project, tasks from different projects can be linked directly. This function is available only with Rillsoft Integration Server.

Note

With cross-project dependencies, successors are not always moved automatically. Negative intervals may arise and must be checked manually.

Check and accept cross-project dependencies

Open Project > Rillsoft Integration Server > Cross-project links.

Cross-project dependencies in a summary project

The table shows all links between projects with these values:

Column

Meaning

Move

If selected, the calculated delay is aligned with the approved delay.

Outgoing project/task

Predecessor of the dependency.

Incoming project/task

Successor of the dependency.

Start

Shows when the dependency starts.

Finish

Shows when the dependency ends.

Reserve

Time interval in absolute time between outgoing and incoming position.

Delay, approval

Approved interval value.

Delay, calculation

Calculated interval value.

Red background indicates a difference between approved and calculated delay.

Click Set automatically to accept all calculated delays automatically.

Create a new cross-project dependency

  1. Choose a dependency type with Start > Insert > Link.

  2. In the Gantt chart, draw a connection from a task in one project to a task in another project.

  3. Enter a delay if required, positive for waiting time or negative for overlap.

  4. Click OK.

Intervals for cross-project dependencies can be entered only in absolute time, for example 10 hours or 2 days.

Merge a Summary Project

If the contents of several projects from a summary project should be saved as one single project:

  1. Choose Project > Rillsoft Integration Server > Merge summary project.

  2. In Rillsoft Integration Server save project, select a virtual folder on the left and projects on the right.

  3. Click OK.

The individual projects are merged into one shared project.

Resolve Resource Differences Before Opening

If Rillsoft Project reports resource differences in individual projects when opening a summary project, open those projects individually first and synchronize them with Project > Project resources > To resource pool. Only then can they be reliably included in a summary project.

More about synchronization:

Next Steps