Dialogs

Dialogs bundle the properties and settings of projects, activities, resources, and server objects. This page describes all tabs of the most important property dialogs in Rillsoft Project.


Project Properties

Open: Start > Properties > Project

Project properties --- General tab

General Tab

Field / option

Meaning

Name

Project name, freely selectable.

Code

Internal project code for synchronisation and filtering.

Start / Finish

Project period. The finish is not necessarily calculated from the activities — it can be set manually.

Cut-off date

Date of the last progress feedback. Only meaningful for running projects. For the initial plan, set it equal to the project start.

Project calendar

Calendar for scheduling the entire project. The button opens the calendar directly.

Category

Project category from the resource pool (Start > Properties > Resources > Project categories).

Priority

Value 1-1000. The higher the value, the more capacity the project receives during capacity balancing in the portfolio. Must not be 0.

Status

Project status from the resource pool (Start > Properties > Resources > Project status).

Customer

Project customer from the resource pool (Start > Properties > Resources > Project customers).

Baseline

Active baseline for the target/actual comparison. Requires a previously saved baseline.

Time step

Time interval for automatic rounding of dates and durations. The maximum value depends on the working times in the resource pool.

Duration (unit of measure)

Working days (project-calendar dependent) or working days (8-hour day).

Effort (unit of measure)

Person days (project-calendar dependent) or person days (8-hour day).

Enter work result for activity

Enables the Quantity and Unit fields in the activity properties (for example 150 m³).

Record effort for activity

Enables effort entry in person days in the activity properties.

Capacity-true planning

Resources are not overloaded. May extend activity durations when employees have non-working days.

Deadline-true planning

The finish date is kept. On non-working days negative effort arises instead of an extension.

Colour

Bar colour for activities and subprojects of this project.

Use for subordinate subprojects and activities

All related activities receive the same colour.

Preferred Teams Tab

Preferred Teams

Restricts capacity planning to specific teams. Only employees of the preferred teams are calculated as available for this project.

Double-clicking a team in the left table adds it to the preferred list.

Shared Device Types Tab

Shared Device Types

Device types that are used by several activities at the same time without summing the quantity. Costs are calculated over the total usage time, not split per activity.

Fields: Quantity, Utilisation, Activities (selection of the activities that share the device type).

Shared Machine Types Tab

Shared Machine Types

Analogous to device types. Machine types that, when several activities overlap in time, are not summed but shared.

Headers And Footers Tab

Headers And Footers

Defines the header and footer for the entire printout (not per page). Areas: Left-Top, Center-Top, Right-Top, Left-Bottom, Center-Bottom, Right-Bottom.

Available fields for header/footer (selection):

Field

Content

View Name

Name of the current view

Project Name / Code

Name and code of the project

Project Category / Project Status / Project Priority

Administrative data of the project

Project Start Date / Project Finish Date

Date data

Project Costs / Project Effort

Total costs and total effort

Project User-Defined Fields

Free-defined fields from the User-Defined Fields tab

Subproject Name / Subproject Start / Subproject Finish

For the subproject level

Cut-off Date / Cut-off Time

Date and time of the cut-off

Last Save Date / Last Save Time

Date and time of the last save

Print Page / Page Number / Print Time

Page numbering and print timestamp

Format Tab

Project properties --- Format

Bar labelling for activities and subprojects. The columns Type (activity or subproject), Position (left, right, top, inside), and Content (variables from the field list) define what is shown on the bars.

Double-clicking a field in the Fields area inserts the variable at the cursor position in the bar label.

Colour Tab

Project properties --- Colour

Resource-dependent bar colour. The table lists all resources scheduled in the project (roles, teams, employees, machines) with the assigned colour.

  • With several resources of different colours, the resource with the higher list position applies.

  • Move up / Move down — adjust the priority of a resource for colour assignment.

  • Set automatically — distribute colours automatically.

  • Restore — reset all colour rules.

User-Defined Fields Tab

Project properties --- User-Defined Fields

Free-definable fields that can be shown in table views and used in printouts.

  • Column Name — field label.

  • Column Text — free text or formula.

Formulas can contain project variables from the Format > Fields tab. Available calculation operations: +, -, *, /.

Notes Tab

Project properties --- Notes

Free text, external links, and file references for the project.

Supported link prefixes: http://, https://, mailto:, ftp://, news:, telnet:, file:.

Buttons: Insert hyperlink from external document, Insert hyperlink from external directory.

Documents (DMS) Tab

Project properties --- Documents

Only available with Rillsoft Integration Server. Shows the DMS directory structure on the left and the directory content on the right.

Actions: Insert, Delete, Download, Refresh. Documents can be dragged and dropped into the right-hand area.

Manage all project documents centrally: Project > Rillsoft Integration Server > Project documents.


Activity Properties

Open: double-click an activity, or select an activity (the properties appear at the bottom).

Activity properties --- General tab

General Tab

Schedule area

Field / option

Meaning

Start (date + time)

Fixed start date. The finish is calculated automatically.

Finish (date + time)

Fixed finish date. The start is calculated automatically.

Lock

The date is not changed during automatic scheduling (for example optimisation, moving).

Mark as milestone

The duration is set to zero. Milestones appear as a diamond in the Gantt chart.

Activity calendar area

Field / option

Meaning

Activity calendar

Calendar for this activity if it differs from the project calendar.

Ignore team and employee calendars

The calendars of the assigned resources are ignored for this activity.

Start activity only at the start shift

The activity may only start at the beginning of a shift.

Display in one row

Several activities one after another in one row, independent of the hierarchy.

Effort type and calculation mode

These fields appear only if Record effort for activity is enabled in the project properties.

Option

Calculation logic

Fixed duration

The duration stays constant. On resource changes the effort is recalculated.

Fixed effort

The effort stays constant. On resource changes the duration is recalculated.

Fixed effort & duration

Effort and duration stay constant. The quantity and utilisation of the resources are adjusted.

Financing area

Field

Meaning

Completed (%)

Progress of the activity in percent.

Fixed costs

Costs that are not represented through resources.

Invoice amount

Amount for the billing period.

Payment term

Due date in working days after the milestone is completed.

Payment receipt

Date of payment receipt (automatic at 100 % + payment term, correctable).

Colour

Individual bar colour for this activity.

Roles Tab

Activity properties --- Roles

Assigns professional qualifications (roles) to the activity. Prerequisite for qualification-based capacity planning.

Left table — roles created in the resource pool

Filter field: search by role group and code. Entering .. shows only roles already used in the project.

A double-click adds the role to the activity.

Right table — assigned roles

Column

Meaning

Quantity

Required number of employees of this role for the activity.

Utilisation (%)

Degree of utilisation of the role in this activity.

Effort

Effort that this role is to provide in the activity.

Notes

Role-related remark on the activity.

Employees Tab

Activity properties --- Employees

Assigns concrete employees to the activity. Can be filtered on the basis of the assigned roles.

Filter options

  • Activate the checkbox of a role — shows only employees with matching qualification.

  • Field Filter — search by name or code. Entering .. shows only project employees.

  • Preferred teams — shows only employees from teams marked as preferred.

Middle table — available employees

Column

Meaning

Readiness (%)

Possible work performance in the activity period, adjusted for non-working days. Highlighted in red when restricted — mouseover shows the detailed days.

Availability (%)

Possible performance adjusted for activities already assigned in the project.

A double-click assigns the employee.

Right table — assigned employees

Column

Meaning

Productivity (%)

Work performance of the employee (pre-set from the resource pool, overwritable).

Utilisation (%)

Percentage of the employee’s participation in the activity.

Additional load

Increased utilisation on other days due to non-working days (visible only with deadline-true planning).

Absence

Opens a calendar for defining activity-specific absence days.

Effort

Effort of the employee in the activity.

Negative effort

Difference between role effort and employee effort (only with deadline-true planning; red = the next employee takes over the substitution).

Substitute for

Shows for whom the employee is scheduled as a substitute.

Responsible

Marking as the activity owner.

Notes

Employee-related remark on the activity.

Distribute effort dynamically

Only with capacity-true planning and at least two employees of the same qualification. Distributes the effort across the available employees.

Timesheets Tab

Activity properties --- Timesheets

Read-only in Rillsoft Project. Feedback is entered through the Rillsoft Integration Server.

Personnel table — all assigned employees with Target, Actual, and Open (effort).

Timesheets table — day-by-day display for the employee selected on the left, with calendar week, weekday, date, Target, Actual, and shift.

Material Tab

Activity properties --- Material

Assigns material (equipment) to the activity.

Left table — available material — filter search by material group, material type, and code. .. shows only project material. A double-click adds material.

Right table — assigned material

Column

Meaning

Calculation

Fixed / per hour / per man-hour / per quantity — determines the calculation basis of the material demand.

Quantity

Material quantity for the activity.

Notes

Material-related remark.

Devices Tab

Activity properties --- Devices

Assigns devices (device type + device name) to the activity. Structure analogous to the Material tab. Fields: device type, quantity, utilisation, effort, notes.

Machines Tab

Activity properties --- Machines

Assigns the machine park to the activity. Structure analogous to Devices. Fields: machine type, machine park, quantity, utilisation, effort, notes.

Activity properties --- Links

Overview of all links of this activity in three tables:

  • Predecessors — type, number, and name of all predecessors.

  • Successors — type, number, and name of all successors.

  • Incompatible activities — activities that may not be carried out at the same time.

Format Tab

Activity --- Format

Activity-specific bar labelling (overrides the project format for this activity). Fields: type, position, content — analogous to the Format tab of the project properties.

User-Defined Fields Tab

Activity --- User-Defined Fields

Activity-specific additional fields. Name and text value, as in the project properties.

Activity --- Notes & Links

Free text, external links (http://, https://, file:, mailto:, ftp://, news:, telnet:), and file references for the activity. Buttons for external documents and directories; alternatively the context menu.

Documents (DMS) Tab

Activity --- Documents (DMS)

Only with Rillsoft Integration Server. Documents assigned to this activity. Actions: Insert, Delete, Download, Refresh.


Information Dialogs

Open: Start > Properties > Info

Information Dialogs

Shows check views for the current project state:

Tab

Content

Late activities

Activities whose finish is after the cut-off date.

Overloaded resources

Resources with more than 100 % utilisation in a period.

Failed resources

Resources that are scheduled in the project but no longer exist in the resource pool.

Unassigned resources

Activities without a resource assignment.

Partially assigned resources

Activities with role demand that is not fully covered by employees.

Portfolio overview

Overview of all projects in the open portfolio with key figures.

Consistency

Logical check of the project plan for contradictions.

Cross-project links

Deviations between released and calculated delays (summary project / portfolio only).


Server Dialogs (Rillsoft Integration Server)

When operating with the Rillsoft Integration Server, the following dialogs are added:

  • Summary project — list of all summary projects, project assignment, locks, baseline option.

  • Project documents — central management of all project documents with filter.

  • Cross-project links — control and release of cross-project dependencies.

  • Select / synchronise resource pool — comparison and reconciliation of project and pool resources.