Analyze the Critical Path

The critical path is the longest chain of activities that determines the project finish date. Each activity on the critical path has no total buffer: if one of these activities is delayed, the project finish date moves directly.

Show the Critical Path

In the Gantt chart:

  1. Open the Gantt chart.

  2. In the view-specific Gantt Chart Format tab, activate Critical path.

  3. Activities on the critical path are highlighted, usually in red.

  4. The critical links between these activities are highlighted as well.

Gantt chart with highlighted critical path

In the network diagram:

Use the network diagram when you need to understand the logical sequence of the critical chain. In the view-specific Network Diagram Format tab, activate Critical path. The critical path is shown as a highlighted chain of nodes.

Note

The critical path can only be calculated correctly when the schedule is linked completely. Unlinked activities are never shown as critical, even if they are critical from a business point of view.

Total Buffer And Free Buffer

Rillsoft Project calculates buffer values for activities. They show how much room an activity has before it affects later dates or the project finish date.

Buffer type

Meaning

When it matters

Total buffer

How far can the activity move without endangering the project finish date?

Basis for decisions about date shifts.

Free buffer

How far can the activity move without delaying the next successor?

Useful for evaluating local scheduling room.

Activities on the critical path have total buffer = 0.

Buffer values can be shown as columns in the activity table. Right-click a column header and configure the visible columns. In older English UI texts, the same concept can appear as contingency reserve, for example Start, reserve and Finish, reserve.

Reserve time and buffer information in the Gantt chart

Near-Critical Activities

Activities with very little total buffer are not yet critical, but can become critical quickly. Monitor them when:

  • a small resource delay could consume the remaining buffer

  • a buffer of one or two days is small compared with the activity duration

  • a changed dependency could reduce the buffer to zero

Define a practical threshold for monitoring near-critical activities, for example total buffer below five working days.

Use The Critical Path For Decisions

Use the critical path for concrete planning decisions.

Evaluate schedule risk

  • Which critical activity has the most uncertain duration estimate?

  • Where do external suppliers, approvals, or dependencies create risk?

  • Are bottleneck resources assigned to critical activities?

Prioritise resources

  • Bottleneck resources should be assigned first to critical activities.

  • If a critical activity is delayed, check whether additional capacity can reduce its duration.

Prepare optimisation

  • If the calculated finish date is too late, first check activities on the critical path for reducible duration or possible parallel alternatives.

  • Non-critical activities may be moved to free resources for critical work.

Evaluate progress

  • Check regularly whether the critical path has changed.

  • If the critical path changes frequently, the schedule logic may be unstable. Check dependencies and buffer values.

Typical Causes Of An Unclear Critical Path

Symptom

Likely cause

The critical path changes unexpectedly after small edits.

Many activities have almost the same buffer; the schedule logic is too tight.

The critical path does not end at project completion.

Not all activities are linked to the final milestone or finish chain.

No activity is critical.

Dependencies are missing or too many finish dates were set manually.

Almost all activities are critical.

Too many finish-finish links or too little planned buffer.

critical path, buffer, slack, finish date, schedule risk, schedule, gantt, bar chart, timeline, dependency, project manager, pmo