Checklist: Prepare Target/Actual Comparison¶
Goal¶
Make sure that target/actual comparison uses the correct reference status and contains current actual data.


Baseline¶
A baseline is saved.
The correct baseline is selected.
If several planning statuses exist, it is clear whether a normal or dynamic baseline is used.
The baseline was not overwritten accidentally afterwards.

Actual Data¶
Progress is maintained for started tasks.
Completed tasks have 100 percent progress.
Actual effort is entered if effort should be evaluated.
Actual start or finish dates are maintained where relevant.
Reporting Date¶
The reporting date is set.
The reporting date matches the status report.
Progress data was updated for the reporting date.
Evaluation¶
Schedule deviations are checked.
Effort deviations are checked.
Cost deviations are checked.
Critical deviations are documented with cause and corrective action.