  • Edit linkΒΆ

    Links can only be edited as long as the succeeding activity has not yet started.

    In order to change an existing link, do as follows:

    • Mark the link you want to edit by clicking on the line connecting the

      two activities.

    • From the drop down menu Link type select another link type in

      the properties window.

    • If necessary, enter the Delay (positive or negative) by which you

      want to delay the succeeding activity depending on the selected activity type.

    • Click on the button OK.

    Alternatively: You can change the Link type via the context menu of the connecting line.