Rillsoft Project
  • Site
      • Legal notice
      • Introduction
      • Working in networks
      • Work with Project
      • Resource management
      • Project views
      • Project portfolio
      • Project controlling
      • Project management
      • Print
      • Customize program environment
  • Page
      • Edit link
  • « Link activities
  • Delete link »

Edit linkΒΆ

Links can only be edited as long as the succeeding activity has not yet started.

In order to change an existing link, do as follows:

  • Mark the link you want to edit by clicking on the line connecting the

    two activities.

  • From the drop down menu Link type select another link type in

    the properties window.

  • If necessary, enter the Delay (positive or negative) by which you

    want to delay the succeeding activity depending on the selected activity type.

  • Click on the button OK.

Alternatively: You can change the Link type via the context menu of the connecting line.

Back to top

© Copyright 2023, Rillsoft GmbH.
Created using Sphinx 7.0.1.