Insert subprojects from Rillsoft Integration Server templateΒΆ
Insert a new subproject in the end of the activity table
Select the menu item Start > Insert > Subproject from Rillsoft Integration Server template.
The dialogue box Open appears.
Select the project you want to insert.
Set start or end of the subproject.
You cannot assume the whole project but only selected activities as subproject by marking appropriate activities.
Click on the button OK.
Note:
Inserted from the Rillsoft Integration Server-template project should work with the same resource pool as the main project. If there is a resource difference, the message appears.
You should open the project inserted from Rillsoft Integration Server-template separately in Rillsoft Project and switch to the resource pool.
Follow the instructions under Shift to the resource pool.
Insert a new subproject in any place in the Gantt chart
Set the cursor on a field in the Gantt chart where you want to insert a subproject.
Click the right mouse button and select the item from the context menu New subproject from Rillsoft Integration Server template.
Continue as described above.