Project-specific team¶
You can structure team usage by clicking the menu item Start > Outline > Structure using the following criteria:
Team -> Project
Project -> Team
Application of the Project-specific team usage view:
Display of the project’s demand for resources in the form of teams for a project.
Resource allocation from the perspective of teams.
Project-specific calculation of the usage for every single team.
Project-specific calculation of the total efforts and total costs of every single team.
Project-specific visualisation of the teams assignation to activities for a project.
You can use the Project-specific team usage view for the following:
Assign selected activities to a team.
Analyse the team usage for a project by means of filter settings.
Change the timescale.
Quick access to the resource pool.
Context menu in the Project-specific team usage view
Show maximum usage per unit of the time – the maximum required number of personnel resources for each of the work groups / teams per day, week, etc.
Show average usage per unit of the time – the average required number of team resources / teams per day, week, etc.
Show effort per unit of the time – planned effort in employee hours (or employee days, respectively) per day, week, etc.