Timesheets tab on the employee viewΒΆ

Here you can display information about the hours worked for a personnel resource.

Prerequisite You or assigned employees can only enter the confirmations in the Rillsoft Integration Server interface.

Activate the tab Timesheets in the activities properties window.

Activities

All activities assigned to the employee are listed here.

Name Name of the assigned activities

Target shows the effort scheduled in the activities for this employee

Actual shows how much of the planned effort the employee has already spent on the activities

Open - shows open effort in the activities for this employee

Notes Notes

Whether the effort is displayed in person-hours or person-days depends on the project settings.

Timesheets

Here you can see for a activitiy selected on the left how the employee has worked through the task on a daily basis.

Calendar week in which calendar week did the employee work for the activities

Day on which day of the week the employee worked for the activities

Data Date

Target shows the effort planned for this employee on the day and for the activities

Actual shows how much of the planned effort the employee has already completed during the day

Shift Time of day