Timesheets tab on the employee viewΒΆ
Here you can display information about the hours worked for a personnel resource.
Prerequisite You or assigned employees can only enter the confirmations in the Rillsoft Integration Server interface.
Activate the tab Timesheets in the activities properties window.
Activities
All activities assigned to the employee are listed here.
Name Name of the assigned activities
Target shows the effort scheduled in the activities for this employee
Actual shows how much of the planned effort the employee has already spent on the activities
Open - shows open effort in the activities for this employee
Notes Notes
Whether the effort is displayed in person-hours or person-days depends on the project settings.
Timesheets
Here you can see for a activitiy selected on the left how the employee has worked through the task on a daily basis.
Calendar week in which calendar week did the employee work for the activities
Day on which day of the week the employee worked for the activities
Data Date
Target shows the effort planned for this employee on the day and for the activities
Actual shows how much of the planned effort the employee has already completed during the day
Shift Time of day