Control of project financingΒΆ

image0

In order to evaluate the project financing, proceed as follows:

  • For the gantt chart open an additional break-even chart in the menu

    item Start > Additional views > break-even chart.

image1

  • Record all expected incoming payments by setting a separate milestone at the date of invoice.

  • The break-even chart contrasts the actual costs with the financing. The the invoices dates are marked at the curve Actual costs.

Note: The financing can be displayed by either the invoices dates or the payment term.

image2

  • You can toggle between the menu items Financing - Invoice date and Financing - Term of payment.

image3

  • Similar to the date of invoice, the dates identical with the payment term are highlighted at the curve Actual cost.

The financing control allows you therefore to detect investment risks (advance financing).