Variance analysis activity propertiesΒΆ
If you click on a row in the table at a Variance analysis view, you can see the differences between the current state of the activities and a state saved in the base plan in the properties window.
These differences can be tracked on the following tabs:
General
Costs
Roles
Employee
Material
Machine type
Machinery
General
Here are the deviations and a summed difference between planned and current values of an activities for
start and finish dates
the effort
the duration
can be seen.
Costs:
On the Costs tab you can see how large the target-actual deviations are for the resource costs.
Roles
Here you get an exact comparison between planned and actual roll requirements in one activities.
Employee
Which staff members were originally scheduled and which are currently assigned to an activities can be seen in the Employee tab.
Material
Here you get an exact comparison between planned and actual material consumption in one activities.
Machine type
Here you get an exact comparison between planned and actual machine type requirements in one activities.
Machinery
Here you get an exact comparison between planned and actual machine requirements in one activities.